STAUNTON – The following is a list of highway work that may affect traffic in the Staunton transportation district during the coming weeks. The Staunton District consists of 11 counties from the Alleghany Highlands to the northern Shenandoah Valley: Alleghany, Bath, Rockbridge, Highland, Augusta, Rockingham, Page, Shenandoah, Frederick, Clarke and Warren.
Scheduled work is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. When traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.
*NEW* or *UPDATE* indicates a new or revised entry since last week’s report.
ALLEGHANY COUNTY
INTERSTATE 64
Mile marker 7 to 12, eastbound – Single lane closures for maintenance to various bridges, 7 a.m. to 7 p.m. through March 31.
Mile marker 13 to 17, eastbound and westbound – Alternating lane closures for maintenance to bridges over Jackson River, 6 a.m. to 6 p.m. through April 30.
*NEW* Mile marker 29 to 24, westbound – Right shoulder closures for drainage maintenance, Monday through Thursday from 7 a.m. to 4:30 p.m.
PRIMARY ROADS
Various roads – Flagger traffic control for tree and debris removal, drainage work, pothole patching, brush cutting and shoulder repairs. Weekdays from 7:30 a.m. to 3 p.m.
SECONDARY ROADS
*UPDATE* Various roads – Flagger traffic control for ditch work, pipe replacement and brush cutting. Weekdays from 7:30 a.m. to 3 p.m.
BATH COUNTY
PRIMARY ROADS
Route 220 (Sam Snead Highway) – Flagger traffic control between Route 651 (Burger Lane) and Route 615 (Main Street, Hot Springs) for utility work, from 8:30 a.m. to 7:30 p.m. through October 6.
Various roads – Flagger traffic control for shoulder repairs and pipe cleaning. Weekdays from 7:30 a.m. to 3 p.m.
SECONDARY ROADS
Various roads – Flagger traffic control for brush cutting and pipe cleaning. Weekdays from 7:30 a.m. to 3 p.m.
ROCKBRIDGE COUNTY
INTERSTATE 64
*UPDATE* Mile marker 46 to 48, eastbound – Right shoulder closures for drainage maintenance, Thursday and Friday from 7 a.m. to 11 a.m.
*NEW* Mile marker 52 to 55, eastbound and westbound – Overnight lane closures for inspection of bridge over Route 602 and Kerrs Creek, Monday night from 8 p.m. to 7 a.m.
*NEW* Mile marker 55 to 57, eastbound and westbound – Single lane closures for inspection of bridge over Route 763 and Mill Creek, Friday from 8:30 a.m. to 4:30 p.m.
INTERSTATE 81
*NEW* Mile marker 176 to 178, northbound and southbound – Overnight lane closures for inspection of bridges over Route 692 (Cedar Creek Road), Sunday and Monday nights (March 12-13) from 8 p.m. to 7 a.m.
*NEW* Mile marker 205 to 200, southbound – Right shoulder closures for brush removal, Monday through Thursday from 7 a.m. to 4:30 p.m.
PRIMARY ROADS
*NEW* Route 11 (Lee Highway) – Southbound alternating lane closures between Conifer Lane and Route 1025 (Boundary Line Lane) for pavement widening, guardrail improvements, installation of rumble strips and pavement markings, March 13 – April 13 from 6 a.m. to 8 p.m.
Route 42 (Virginia Avenue) – Flagger traffic control between Goshen town line and Route 39 (Maury River Road) for maintenance to bridge over Calfpasture River, 7 a.m. to 5 p.m. through March 24.
Various roads – Flagger traffic control for pipe replacement, ditch work, tree removal, shoulder repairs, pavement patching and brush cutting. Mobile lane closures for mowing. Weekdays from 7:30 a.m. to 3 p.m.
SECONDARY ROADS
Route 699 (Agners Mill Road) – Traffic redirected onto temporary causeway between Route 608 (Forge Road) and dead end for replacement of bridge over a tributary to Maury River, 7 a.m. to 5 p.m. through April 6.
Various roads – Flagger traffic control for grading, pipe replacement, ditch work, tree removal, pavement patching, shoulder repairs and brush cutting. Mobile lane closures for mowing. Weekdays from 7:30 a.m. to 3 p.m.
HIGHLAND COUNTY
PRIMARY ROADS
Various roads – Flagger traffic control for pothole patching, brush cutting and shoulder repairs. Weekdays from 7:30 a.m. to 3 p.m.
SECONDARY ROADS
Various roads – Flagger traffic control for brush cutting, pipe cleaning, tree removal, adding stone to unpaved roads and ditch work. Weekdays from 7:30 a.m. to 3 p.m.